Journal
A dated, updatable log of this project's real milestones, decisions, and open questions -- written as they happen, not reconstructed afterwards.
Phase 4 closed -- the checkpoint came back refined, not confirmed
Phase 4 was the reliability pass: a single iteration that authored the dated Phase 3 journal entry and applied the four refinements the Phase 3 checkpoint carried forward. The iteration path ran through development, review, delivery, and checkpoint on one planned iteration -- and the checkpoint came back refined, not confirmed as-is, because the deployed slice still carried a wrong statistic and a dark-mode diagram visibility defect. This is that account, with those two findings stated as open.
- #phase-4
- #checkpoint
- #journal
Phase 3 closed -- the site finally tells its own history accurately
Phase 3 was the documentation phase: the dated Phase 2 journal entry, the three Factory process diagrams, the Infrastructure / Lab expansion, the homepage status section, and a site-wide cleanup and publication audit. It also recorded the one time the experiment ran off a stale baseline, how the corrected run was carried, and the four minor corrections the checkpoint handed to the next phase. This is that account.
- #phase-3
- #checkpoint
- #journal
Phase 2 closed -- four iterations in, and the operational foundation is real
The second Controller run took four sequential development iterations to an approved checkpoint -- and it took 108 role dispatches, of which 24 succeeded. This is the honest account of what Phase 2 did, what it spent to do it, and what it proved and did not prove.
- #phase-2
- #checkpoint
- #milestone
Gate 2 approved, and the first two Phase 1 iterations are in
Architecture and Implementation Plan cleared Gate 2 after a first review found real gaps; the AstroWind scaffold and the site's dark, technical theming are both built and merged. This page and the rest of the content model are the next iteration.
- #gate-2
- #phase-1
- #milestone